Airport Development & Planning

UPCOMING PROJECTS


Auburn Tenants and Stakeholders can look forward to a new extension on Runway 16/34 that brings our dimensions up from 3,400' x 75' to 3,841' x 75'. This project is slated to begin Spring of 2020 and hopes to cater to more mid sized Turbo Prop Aircraft (Pilatus PC-12s) as well as some smaller corporate jets (Citation Mustangs). 


2020

  • Runway Extension and Lighting Project - View Diagram (PDF)
    • Timeline: April 1st - June 30th 
    • The runway will be closed only during the runway/signage       installation phase and the remarking of the runway. These closures will be daily from 5:00pm - 10:00am beginning Sunday evenings and ending Friday mornings (The airport will be open during the weekend. Weekdays it will be open from 10:00am - 5:00pm)
    • During the installation of the new runway ends the runway will remain open with displaced thresholds 
    • Runway lights will be unavailable for the duration of the 75 calendar day construction period 
    • 30 days after project completion, there will be an additional 4 days of work for the final paint marking application 
  • Airport Gate Upgrade Project
  • Westside Environmental 
  • Hangar Upgrades

2021

  • Hangar Facility Construction

2022

  • Pavement Overlay of Runway 16-34
    • Expect a one month full closure of the runway
  • Magnetic Variation change to Runway 17-35 
  • Taxiway A fog seal, airfield pavement crack sealing and patching 
  • PAPI Installation 
  • Runway 34 Runway Safety Area Grading 
  • Open T-hangars Retrofit and Upgrade 

2025

  • Installation of an Automated Weather Observation System (AWOS)
  • Rotating Beacon Installation 
  • Airfield Lighting Emergency Generator 


Development opportunities exist at the Auburn Municipal Airport. For more information, please contact us

image28

Airport Layout Plan (ALP)

Auburn's ALP as shown in the 2015 Airport Master Plan

The Airport Layout Plan is a graphic or series of graphics and diagrams that accompany an airport's Master Planning document to show both current and planned facilities at an airport. The current displayed Layout Plan came with the 2015 Airport Master Plan and is a good means of visually showing the most up to date plans for Dick Scobee Field.


If you have any questions about this document, feel free to email airport@auburnwa.gov or call (253)-333-6821.